Brickwork estimating: number of bricks, mortar and wastage
Bricks per cft and per cum for Bangladeshi standard bricks, mortar volume and cement for 1:4 and 1:6, and how to measure walls with deductions.
Prime Base Engineering · 17 October 2026 · 2 min read
Brickwork remains the most common walling in Bangladesh. Its estimate has two parts — bricks and mortar — and one discipline: deducting openings.
The standard brick
The common first-class brick measures about 9½" × 4½" × 2¾" (240 × 115 × 70 mm). With a 10 mm (⅜") mortar joint, the nominal size becomes about 10" × 5" × 3".
Bricks per unit volume
- Volume of one nominal brick = 10 × 5 × 3 = 150 in³
- 1 cft = 1,728 in³ → 11.5 bricks per cft
- 1 cum ≈ 35.31 cft → about 406 bricks per cum (by the metric nominal 250 × 125 × 75 mm, about 427)
Add 3–5 % breakage and wastage.
Mortar
The mortar fills the joints and the frog. A practical figure is 0.30 cft of dry mortar per cft of brickwork (wet mortar about 0.22–0.25 cft, × 1.33 dry factor).
For 1:4 mortar (parts = 5):
- per 100 cft of brickwork: dry mortar = 30 cft
- cement = 30 / 5 = 6 cft = 4.8 bags
- sand = 24 cft
For 1:6 (parts = 7): cement = 4.3 cft = 3.4 bags, sand = 25.7 cft.
Measuring walls
- Measure each wall's length along its centre line (avoid double counting corners).
- Multiply by height and thickness: 10" (250 mm) and 5" (125 mm) walls are typical.
- Deduct doors, windows, lintels, beams and columns that interrupt the wall.
Worked example
A 10" wall, 40 ft long and 10 ft high, with two 3' × 7' doors and three 4' × 4' windows:
- Gross = 40 × 10 × 0.833 = 333.3 cft
- Doors = 2 × 3 × 7 × 0.833 = 35.0 cft
- Windows = 3 × 4 × 4 × 0.833 = 40.0 cft
- Net = 258.3 cft → 2,970 bricks + 4 % = 3,090 bricks; mortar 77.5 cft dry; at 1:4, 12.4 bags of cement
Half-brick walls
5" walls are usually measured by area (sft or sqm) in the BOQ, with bricks and mortar per sft derived the same way.
In EstiMatrix
Use − Add deduction rows for openings; they turn red and subtract automatically. The material requisition sums bricks, cement and sand from every brickwork analysis.
#brickwork#masonry#mortar
Related articles
What is a bill of quantities (BOQ)? A practical guide for Bangladesh
What a BOQ contains, who prepares it, how it differs from an estimate and a rate analysis, and how to structure one for PWD and private projects.
30 Oct 2026 · 2 min read
Construction cost per square foot in Bangladesh (2026): thumb rules and sanity checks
Indicative cost per sft for residential, commercial, factory and PEB buildings; steel and cement per sft; and how to use thumb rules to catch estimating errors.
28 Oct 2026 · 2 min read
PWD Schedule of Rates explained: editions, zones and how to use them
Civil, E/M, retrofitting and lift schedules; the four rate zones; editions in force; basic rates; and how to apply SoR rates in metric and imperial projects.
27 Oct 2026 · 2 min read