Plaster quantity calculation: area, mortar, cement and deductions
Measure plaster area correctly, apply the deduction rules for openings, and work out cement and sand for 12 mm and 20 mm plaster in 1:4 and 1:6.
Prime Base Engineering · 15 October 2026 · 2 min read
Plaster is measured by area and priced per sqm or sft, but its materials depend on thickness and mix.
Measuring the area
- Measure each face separately: inside and outside of external walls, both faces of internal walls.
- Ceilings and beam soffits are usually separate items.
- Deduct openings larger than the limit your method of measurement sets — commonly openings over 0.5 sqm (about 5 sft) are deducted; jambs, sills and soffits (returns) are then measured and added.
Mortar volume
Wet mortar = area × thickness. Dry mortar = wet × 1.33, plus about 20 % for joint filling, uneven surfaces and droppings on rough brickwork (many engineers use a combined factor of 1.5–1.6 over wet).
For 100 sft of 12 mm (½") plaster:
- wet = 100 × 0.5 / 12 = 4.17 cft
- dry ≈ 4.17 × 1.33 × 1.2 = 6.65 cft
At 1:4: cement = 1.33 cft = 1.06 bags, sand = 5.32 cft. At 1:6: cement = 0.95 cft = 0.76 bags, sand = 5.70 cft.
Per sqm
For 1 sqm of 12 mm plaster at 1:4: wet 0.012 cum, dry ≈ 0.019 cum, cement ≈ 0.0038 cum = 0.11 bag, sand 0.015 cum.
Thickness guide
| Location | Typical thickness |
|---|---|
| Internal walls | 12 mm |
| External walls | 16–20 mm |
| Ceilings | 6–10 mm |
Worked example
A room 14' × 12' with walls 10' high, one 3' × 7' door and one 5' × 4' window:
- Walls = 2 × (14 + 12) × 10 = 520 sft
- Deduct door 21 sft and window 20 sft → 479 sft
- Add returns (jambs) if your method requires them.
In EstiMatrix
Area items show Nos, Length and Width only. Enter openings as deduction rows; link a second coat or a paint item to the plaster rows with linked measurements so the areas always match.
#plaster#finishing#mortar
Related articles
What is a bill of quantities (BOQ)? A practical guide for Bangladesh
What a BOQ contains, who prepares it, how it differs from an estimate and a rate analysis, and how to structure one for PWD and private projects.
30 Oct 2026 · 2 min read
Construction cost per square foot in Bangladesh (2026): thumb rules and sanity checks
Indicative cost per sft for residential, commercial, factory and PEB buildings; steel and cement per sft; and how to use thumb rules to catch estimating errors.
28 Oct 2026 · 2 min read
PWD Schedule of Rates explained: editions, zones and how to use them
Civil, E/M, retrofitting and lift schedules; the four rate zones; editions in force; basic rates; and how to apply SoR rates in metric and imperial projects.
27 Oct 2026 · 2 min read