Concrete material quantities: the 1.54 dry-volume factor and cement bags
How to work out cement, sand and stone chips for 1:2:4, 1:1.5:3 and 1:3:6 concrete, why the dry volume is 1.54 times the wet volume, and bag conversions.
Prime Base Engineering · 19 October 2026 · 2 min read
Nominal-mix concrete is specified by volume ratios — cement : sand : coarse aggregate — such as 1:2:4. Turning a wet volume of concrete into dry materials needs one factor.
Why 1.54?
Dry loose materials contain voids. When water is added and the mix is compacted, the fine particles fill the voids between the coarse ones and the volume shrinks. Experience shows the dry volume needed is about 52–57 % more than the finished wet volume. The usual working value is 1.54 (EstiMatrix's default; change it per project under Tools → Dry-to-wet factors).
The method
- Dry volume = wet volume × 1.54
- Sum of ratio parts = 1 + 2 + 4 = 7 (for 1:2:4)
- Cement = dry volume × 1/7, sand = × 2/7, aggregate = × 4/7
Cement bags
A 50 kg bag of cement occupies about 1.25 cft (0.0347 cum) — cement's bulk density is roughly 1,440 kg/m³. EstiMatrix uses 1 bag = 1.25 cft = 50 kg by default.
Worked example — 1 cum of 1:2:4
- Dry volume = 1.54 cum
- Cement = 1.54 / 7 = 0.220 cum = 6.3 bags (≈ 317 kg)
- Sand = 0.440 cum
- Stone chips = 0.880 cum
Worked example — 100 cft of 1:1.5:3
- Dry volume = 154 cft; parts = 5.5
- Cement = 28.0 cft = 22.4 bags
- Sand = 42.0 cft
- Aggregate = 84.0 cft
Quick reference per cum (wet)
| Mix | Cement (bags) | Sand (cum) | Aggregate (cum) |
|---|---|---|---|
| 1:3:6 (lean) | 4.4 | 0.44 | 0.88 |
| 1:2:4 | 6.3 | 0.44 | 0.88 |
| 1:1.5:3 | 8.1 | 0.42 | 0.84 |
Add wastage
Add 1.5–2.5 % for cement and 2.5–5 % for sand and aggregate depending on site handling. EstiMatrix applies wastage per material class.
Designed mixes
For concrete specified by strength (for example 25 or 40 MPa) the proportions come from the mix design, usually by weight. Use the mix design's cement content per cum rather than nominal ratios.
Mortar
Mortar uses a smaller factor — about 1.33 — because sand alone has fewer voids to fill. See brickwork estimating and plaster quantities.
#concrete#cement#material quantity
Related articles
What is a bill of quantities (BOQ)? A practical guide for Bangladesh
What a BOQ contains, who prepares it, how it differs from an estimate and a rate analysis, and how to structure one for PWD and private projects.
30 Oct 2026 · 2 min read
Construction cost per square foot in Bangladesh (2026): thumb rules and sanity checks
Indicative cost per sft for residential, commercial, factory and PEB buildings; steel and cement per sft; and how to use thumb rules to catch estimating errors.
28 Oct 2026 · 2 min read
PWD Schedule of Rates explained: editions, zones and how to use them
Civil, E/M, retrofitting and lift schedules; the four rate zones; editions in force; basic rates; and how to apply SoR rates in metric and imperial projects.
27 Oct 2026 · 2 min read